Common claims

“Closed loop”

What it means
A loop can reuse the same water.
What it does not tell you
It does not tell you that no water is lost. A separate cooling tower can evaporate water to remove heat while the loop reuses its water. Ask how the whole campus releases its heat, including on hot days.
What to ask
Which parts, if any, use evaporative cooling?

Sources

“100% renewable”

What it means
The claim may be about yearly purchases or about certificates.
What it does not tell you
By itself, it does not show hourly matching at the site. Check the time period, the region and who owns the certificates.
What to ask
Is this a yearly claim, an hourly result, or a goal for the future?

Sources

“We have a permit”

What it means
A permit allows named activities under conditions. What it covers and the limits it sets both matter.
What it does not tell you
A permit does not prove that the project has no harmful effects. Operating reports and inspections help show whether the conditions were met.
What to ask
What does this permit cover? Where are the compliance results?

Sources

“Water positive”

What it means
It is a claim to replenish (put back) water. Such a claim needs its own method, place, timing and delivered benefits.
What it does not tell you
By itself, it does not show that the site’s supply can meet a peak-day or drought demand.
What to ask
Which watershed benefits, and when? How were the benefits checked?

Sources

Words, A to Z

Acre-foot

A measure of water: enough to cover one acre of land one foot deep. It equals 325,851 gallons.

Adopted, binding and enforceable

Adopted means a public body has formally approved it, so it is no longer a draft or a proposal. Binding means the company is required to follow it. Enforceable means a named authority can act if the company does not.

Air permit, draft and exemption

An air permit is a legal document that sets the pollution rules a site must follow. State and local agencies issue most of them. An application or a draft is not a final permit, and an exemption is an agency’s finding that no permit is required.

Backup generator and turbine

A backup generator is an engine that makes electricity when grid power is out. A turbine is a machine that spins to make power. A data center can use engines and turbines for its main power as well as for backup.

Campus, phase and buildout

Also called build-out

A campus is a group of data center buildings on one site. Large sites are built in stages, called phases, and buildout is the full site once every stage is built. Ask which phase a number covers.

Closed loop

Also called closed-loop cooling

Pipes that send the same water around again and again to carry heat away from the computers. The loop still has to pass that heat on. Ask where the heat goes next, because a cooling tower may evaporate water to remove it.

Compliance

Following the rules in a permit or an approval. A compliance report or an inspection shows whether the rules were followed in a stated period.

Cost allocation

How a utility’s costs are divided among groups of customers. An adopted tariff or agreement can assign named costs to one large customer.

Decibel (dB and dBA)

Also called A-weighted decibel

A decibel (dB) is the unit for how strong a sound is. The “A-weighted” version, dBA, is adjusted to match how loud a sound seems to the human ear. A small rise in the number means a large rise in noise.

Developer, operator and tenant

A developer builds the site and an operator runs it. A tenant is a company that rents space there for its own computer equipment. These can be different companies.

Energy certificates (RECs)

Also called renewable energy certificate, REC

A renewable energy certificate (REC) is a record that one megawatt-hour of renewable electricity was made and put on the grid. Whoever owns the certificate can claim that renewable power. Retiring a certificate means using it for a claim, so that nobody else can claim it.

Evaporative cooling and cooling towers

A way to remove heat by letting water evaporate into the air. A cooling tower works this way. The water that evaporates has to be replaced, and the added water is called makeup water.

Financial security

Also called collateral, credit support

Money or a guarantee that a large customer gives the utility, such as a cash deposit or a letter of credit. It is meant to cover costs if the project is delayed, is dropped, or uses less power than forecast.

Generation, transmission, distribution and connection

Also called interconnection

Generation is making the power, and transmission is moving it long distances on high-voltage lines. Distribution is delivering it to customers. Connection is linking the site to the grid.

Grid and grid region

The grid is the network of power lines and substations that links power plants to the people who use electricity. A grid region is one part of it. Ask which grid region a clean-power claim covers.

Kilowatt-hour (kWh)

A unit of electricity used over time. One kilowatt-hour is one kilowatt used for one hour. One megawatt-hour is 1,000 kilowatt-hours.

Land-use decision and rezoning

Also called zoning map amendment

A land-use decision is a local government’s final decision that applies its land-use plan or rules. Rezoning changes the zone a piece of land is in, and so the uses allowed there. A decision can be an approval or a denial, and it can later be amended, appealed or reversed.

Low-frequency and tonal sound

Also called prominent discrete tone

Low-frequency sound is deep, low-pitched sound, such as a hum. Tonal sound has one pitch that stands out from the sound around it. Ask whether the noise study covers both.

MW and MWh

A megawatt (MW) measures power at one moment. A megawatt-hour (MWh) measures energy used over time: a site that runs at 1 MW for one hour uses 1 MWh. Planned capacity is not the same as measured yearly use.

Other customers (ratepayers)

Also called ratepayers

The homes and businesses that pay a utility’s rates, often called ratepayers. If demand falls short of the forecast or a project closes, they may be left with costs.

Permitted limit and actual emissions

Also called potential to emit

A permit sets the most pollution a site is allowed to release. That upper limit is not the amount the site did release. Actual amounts come from operating reports.

Potable water

Also called drinking water

Water that is fit to drink.

PUE (power usage effectiveness)

Also called power usage effectiveness

PUE compares all the electricity a site uses with the part its computers use. It shows the overhead. It does not show total use, carbon emissions or how much useful computing was done.

Reclaimed (recycled) water

Also called reclaimed wastewater, recycled water

Treated wastewater that is used again, for example for cooling or for watering land.

Renewable and carbon-free

Renewable sources, such as sun and wind, restore themselves in a short time. Carbon-free sources make electricity without giving off carbon dioxide. Nuclear power gives off no greenhouse gases while making power but is not renewable, so ask which sources a claim counts.

Replenishment and “water positive”

Also called water replenishment

Replenishment means returning water to the area around a site, and “water positive” is a claim to replenish water. Such a claim needs its own method, place, timing and proof of the benefits delivered. By itself, it does not show that the local supply can meet the site’s demand.

Tariff and stranded costs

A utility tariff sets the rates and the terms of service. Stranded costs are costs that still have to be paid for when infrastructure is no longer needed as expected. Contracts can say who carries that risk, with exceptions that are worth reading.

Utility commission, order, docket and rate case

Also called public service commission, public utility commission

A utility commission is the public body that regulates utility rates, and an order is its written decision. A docket is its file of all the documents in one case. A rate case is the process that sets what a utility may charge.

Water utility and capacity study

Also called public water supplier

The water utility is the public body or company that supplies water to a town. A capacity study is its review of how much water it can supply.

Water withdrawal and consumption

Also called consumptive use

Withdrawal is water taken from a source. Consumption is the part that leaves the local water environment, for example when it evaporates. Water that is returned somewhere else may still affect the local supply.

Watershed

The area of land that drains to one stream, river or lake.

WUE (water usage effectiveness)

Also called water usage effectiveness

WUE compares the water a site uses with the electricity its computers use, often in liters per kWh. Check what the figure covers and for what time period. Ask for the total amount of water too.

Yearly and hourly matching

Also called annual matching, 24/7 matching

Yearly matching, often called annual matching, balances the power made and the power used over a whole year. Hourly matching compares them hour by hour. Ask which grid region, which energy sources and what percentage are covered.